Methanex G-2 Mechanical Project

Geismar, Louisiana

Contract Value: $79,000,000

Duration:

  • Mechanical construction began October 1, 2014, and was completed on December 9, 2015.  
  • Full mechanical completion was achieved on December 23, 2015, with methanol being produced on December 27, 2015. 

Turner Industries was responsible for the installation of all G-2 mechanical works for the project. Turner set all heavy haul transported equipment, which included the setting of the 8 pipe rack modules, 10 process unit modules, 12 lager vessels and compressors. 

turner’s mechanical scope included

  • Structural steel erection 
  • Setting of all towers, drums, heat exchangers, pumps, compressors, flare stacks and the piping that interconnects them
  • Coordination of various other contractors’ work including metal building erection and roofing, portable onsite machining, lead abatement, air conditioning installations and NDE services
  • Workhours: 1,226,592 
  • Percentage of Labor Self-Performed: 50% 

turner’s self-performed work

  • 2 Compressors 
  • 4 Lube Oil Skid Units 
  • 11 Exchangers (New) 
  • 3 Filters 
  • 13 Towers 
  • 2 Vessels 
  • 5 Columns (Reused) 
  • 27 Exchangers (Reused) 
  • 1 Reactor (Reused) 
  • 1 Flare stack(Reused) 
  • 1 Vent stack (Reused)  
  • 21 Vessels (Reused) 
  • 11 Skids (Reused) 
  • 1 Generator (Reused) 