Sasol 2021 Ethylene Turnaround
The 2021 Ethylene Turnaround at the Sasol Lake Charles Chemical Complex in Westlake, Louisiana, was 50-day event to perform maintenance, repairs, and capital projects.
Turner services utilized included: Scaffolding, Insulation, Painting, and Abatement (SIPA), Piping, Mechanical, Civil, Structural, Fabrication, I & E, Turnaround Services Group, Crane and Rigging and Turner Specialty Services (NDE/Vacuum Trucks/Torquing/Hydro Blasting/Bundle Extraction/Rope Access).
Location: Lake Charles, Louisiana
turnaround quick facts
- Duration: 50 Days
- Peak Headcount: 1,070
- Workhours: 468,028
- Field Packages: 886
- Scaffold Pieces: 223,023
- Welds: 2,343 – Pass rate 100%
- Bolt-Ups: 4,389
- OSHA Recordable: ZERO