Westlake Chemical – CA/VCM Major Turnaround
Plaquemine, Louisiana
project quick facts
- Duration: January 2022 – August 2022
- Contract Type: Time and Materials
- Workhours: 251,352
- Percentage of Labor Self-Performed: 98%
- OSHA Recordables: ZERO
- Contract Value: $25 MM
- Subcontractors: 2
turner self-performed
Mechanical and Piping:
- Fabricated and installed 21,000 feet of pipe
- 4 exchangers (open, clean, inspect)
- 4 towers (opened, cleaned, inspect, removed trays and install new)
- 15 tons of steel erected
- 18,000 Ft piping demoed
- 6,495 welds / 94,439 weld inches with less than 1.5% rejection rate
Scaffolding, Insulation, Painting, and Abatement
- 400+ Scaffolds Built
- 3,500 Linear Ft. of Piping Insulation
- 39,000 Sq. Ft. of Vessel Insulation
- 2,500 Linear Ft. of Piping (Blast and Paint)
- 650 Weld Touch-Up Paint In Unit
Civil
- 28 Pump Bases Demolished and Repoured
- 6 Equipment Pads
- 10,000 Sq. Ft. Area Paving
- 450 Grout Pads
- Approx. 150 yards of concrete poured, all brought in with Georgia buggies due to tight locations and no access for trucks
Crane and Rigging: Over 24 total cranes to support the overall project
- 600-ton and 500-ton for lifting fin fans over unit