ExxonMobil – Polypropylene Growth Project
ExxonMobil – Polypropylene Growth Project
Location: Baton Rouge, Louisiana
- Contract Value: 260MM
- Contract Type: EPC Consortium
- Workhours: 2.9MM
- Duration: January 2019 – September 2022
- Percentage of Labor Self Performed: 95%
- Subcontractors: 32
turner self-performed
- Site Preparation/Excavation: Excavated roughly 55,300 cubic yards of dirt
- Civil: 14,740 cubic yards of concrete and 1,210 tons of rebar
- Structural Steel: 3,430 tons split between new structures and additions to existing ones
- Equipment: Setting 366 total pieces of process equipment and 7 modules
- Hydro Testing: 631 hydro test packages
- Painting: 34,180 square feet of paint touch up
- Insulation: 29,600 linear feet of piping insulation
- Scaffolding: Erected over 592,000 leg feet of scaffold
- Piping: 166,396 linear feet of piping
- Fabricated, barged 7 modules from our 415 Yard