Kuraray Eval Spring 2021 Turnaround

In 2021, Turner was selected to execute the Spring Kuraray Eval Turnaround in Pasadena, Texas. This was the second time Turner was tasked to perform this event, the first time being back in 2018. 

Location: Pasadena, Texas

scope of work

  • Pipe Fabrication 
  • Mechanical 
  • Piping 
  • Electrical and Instrumentation  
  • SIPA Work Packages  

project quick facts

  • Duration: 25 Days 
  • Peak Headcount: 285 
  • Hours Worked: 140,000 
  • OSHA Recordables: ZERO 