Westlake Job Completed Ahead of Schedule
Turner Industries employees at Westlake Petro just wrapped up a complete furnace retubing, three days ahead of the original 21-day schedule.
This project required extensive planning, coordination, and technical expertise, all of which were expertly executed by our team. This was a true demonstration of what teamwork is. The synergy among the team members, coupled with their expertise and commitment to excellence, made this project a success.
Matthew Clift, superintendent for Turner Industries
PROJECT QUICK FACTS
-
18 DaysDuration
-
31Workers
-
185Total Welds
-
0%Rejection Rate